The building project is located directly on the Loosdrecht lake
district, which is connected via the river Vecht with the Markermeer and
thereby with Amsterdam, the Ijsselmeer and the North Sea. Originally the area
was a marshland used for peat extraction until it was turned into a recreational
area in the 20th century. The challenge of the project was to use the thermal
energy stored in the water to heat and cool a single-family house with direct
access to the lake. The building, built in 2010 (rebuilt in 2021), has very
good insulation values, double-glazed windows (HR++), underfloor heating and
low-temperature fan-assisted radiators. In the course of this project, a
brine-to-water heat pump was retrofitted.





For the efficient operation of the heating system the heat pump with 9 kW heating capacity requires an environmental extraction capacity of approx. 7 kW at a volume flow of 2000 l/h. Due to the minimum temperature of the Loosdrecht Lake of approx. 4° C and the on-site operations, two FRANK WET water heat exchangers type 1 are used here. Each of them has a capacity of approx. 4 KW at a volume flow of 1000 l/h. The installation of the heat pump and the heat exchangers was done in two steps:
Step 1
The installation of the heat pump in the garage integrated in the residential building was carried out by the building owner. The existing piping of the old gas heating system could be used for the most part.
Step 2
The FRANK water heat exchangers were fixed in the lake at a depth of approx. 2 m using buoyancy protection devices. In addition, the complete piping with the manifold and collector as well as the heat pump in the garage.
Further details
The supply and return pipes (d 40 SDR 11 PE 100-RC) of the two FRANK
water heat exchangers are each approx. 50 m long and were connected to a
plastic brine manifold type 3060 in the garage with a material bond. The
resistant PE 100-RC pipes could be laid with little effort in trenches approx.
0.5 m deep and led into the building by means of core drillings. During
subsequent operation a carrier medium (25% ethylene-glycol-water mixture)
circulates in the pipe system between the heat exchangers and the water heat
pump.
All connections of the system, starting with the heat exchangers up to the heat
pump, were realized with permanently tight heating coil welds. FRANK
impact-press seals were used for the subsequent sealing of the pipe penetration
through the masonry.
Heat Source Outlet Temperature [°C], Outside Air Temperature [°C] and Heating Power [W] between 04.01.2023 and 09.01.2023

Delta Temperature Brine [°C] and Running COP between 04.01.2023 and 09.01.2023


The water heat exchangers are lowered by means of a 40 kg steel weight, which is attached to the outer shell of the WET with stainless steel cables.

Insulated modular brine manifold type 3060.

This project is supported by the German Federal Ministry for Economic Affairs and Climate Action as part of the Renewable Energy Solutions Programme of the German Energy Solutions Initiative.
German Energy Agency (dena)
The German Energy Agency (dena) is a centre of excellence for the applied energy transition and climate protection. dena studies the challenges of building a climate-neutral society and supports the German government in achieving its energy and climate policy objectives. Since its foundation in 2000, dena has worked to develop and implement solutions and bring together national and international partners from politics, industry, the scientific community and all parts of society. dena is a project enterprise and a public company owned by the German federal government. dena’s shareholders are the Federal Republic of Germany and the KfW Group. www.dena.de/en
German Energy Solutions Initiative
With the aim of positioning German technologies and know-how worldwide, the German Energy Solutions Initiative of the Federal Ministry of Economics and Climate Action (BMWK) supports suppliers of climate-friendly energy solutions in opening up foreign markets. The focus lies on renewable energies, energy efficiency, smart grids and storage, as well as technologies such as power-to-gas and fuel cells. Aimed in particular at small and medium-sized enterprises, the German Energy Solutions Initiative supports participants through measures to prepare market entry as well as to prospect, develop and secure new markets. www.german-energy-solutions.de/en
Renewable Energy Solutions Programme (RES Programme)
With the RES programme, the Energy Export Initiative of the Federal Ministry of Economics and Climate Action (BMWK) helps German companies in the renewable energy and energy efficiency sectors enter new markets. Within the framework of the programme, reference plants are installed and marketed with the support of the German Energy Agency (dena). Information and training activities help ensure a sustainable market entry and demonstrate the quality of climate-friendly technologies made in Germany. www.german-energy-solutions.de/res-programm.html